Auftraggeber

Busbetrieb Olten Gösgen Gäu AG

Architektur

Itten+Brechbühl AG (ab Phase 32/ Bauprojekt), W. Thommen AG (bis Phase 31/ Vorprojekt)

Planung/Ausführung

2020-2023, Umbau und Erweiterung in drei Etappen während laufendem Betrieb

Nutzung

Nahverkehrsbetrieb: Betriebszentrale mit Fahrdienstdisposition, Busdepot, Reparatur- und Unterhaltsdienst, Verwaltung (insgesamt rund 180 Mitarbeitende)

Geschossfläche

8560 m2

Gebäudevolumen

47 000 m3

Back

Wangen bei Olten, Switzerland

Extension and conversion of the BOGG bus depot

Program Conversion and expansion in three stages during ongoing operations: operations center with dispatching service, new bus hall for over 40 regular buses with charging stations incl. washing facility, repair and maintenance service, administration, water treatment and photovoltaic system, groundwater use for heating/cooling, parking spaces for cars and bicycles incl. charging stations for electric vehicles, underground car park
Client Busbetrieb Olten Gösgen Gäu AG
Planning / Construction 2020-2023
Services provided by IB
  • Construction Planning
  • Architecture
Architecture W. Thommen AG (bis Phase 31/Vorprojekt)
Itten+Brechbühl AG (ab Phase 32/Bauprojekt)
Surface area 8'560 m2
Construction volume 47'000 m3

The bus depot in Wangen near Olten is the operating center of the bus company Busbetrieb Olten Gösgen Gäu AG (BOGG) with dispatching, repair, and maintenance services as well as the entire administration. The scope of the project included conversion, extension, and technical modernization of the company building of the bus depot as well as building a new bus hall during ongoing operation. Construction during operation requires a great extent of coordination from all parties involved. All necessary work was carried out in stages to ensure that operation could continue during the construction period and to guarantee vehicle access to the bus hall and workshop bays.

A new bus hall for parking public transport buses at night also contains a vehicle washing facility, a water treatment system, charging stations for new e-buses, an underground parking area for staff, and technical rooms. An additional story and an annex with two workshop bays were added to the existing company building. The new upper floor provides space for customer service, a conference room as well as social and duty rooms for drivers. An additional technical floor was added in the second upper story of the annex.

The bus stop «Kleider Frey» including sanitary facilities was moved directly to the front of the company building within the scope of the conversion. A new bike shelter with charging station for e-bikes has been created near the bus stop for public transport users.

The uniform facade design used for the bus depot, company building, bus stop, and bike shelter endows the building ensemble with a homogenous and modern appearance. The new insulation, modern metal windows, and Venetian blinds also significantly improve the energy efficiency of the existing company building.

More projects